Which of the following are projects?
I Staging an open air concert
II Getting married
III Staying married
Which of the following is correct?
I Projects are about managing change
II Projects are about teamwork
III Projects are about uncertainty
Which of the following is correct?
Which of the following is not a project?
Which of the following is correct?
I Uncertainty and risk are highest at the start of a project
II Each phase in a project has different organisational needs
III Staffing levels begin high in a project then level off during execution and control before dropping quickly as the project draws to a close
Approval to go ahead with a project should not be given unless it satisfies which three criteria?
Which of the following is correct when managing a project?
I All decisions must be directed towards achieving the project objectives
II Only the remaining work can be managed
III All decisions must have the sponsor’s approval