Project communication with the customer is crucial to a project's success. This communication takes place between the executives, project managers, and employees of both the customer and the contractor. The key to success is that the formal communication should go through which of the following people?
Project stakeholders are individuals and organisations who are actively involved in the project, or whose interests may be positively or negatively affected by the project. Based on this definition, which of the following individuals or groups are project stakeholders?
I
The customer
II The performing organisation
III The community where
the project takes place
When a Director of Project Management is making a decision on whether or not a project requires a project manager, the Director should do which of the following?
Which of the following is correct? The swiftest and most effective communications take place among people with:
A programme can be best described as:
On which projects is integration most complicated?
Which of the following is (are) the wrong reason(s) for selecting someone to act as a project manager?
I
Selecting someone simply because of availability
II Selecting someone who
has a command of technology
III Selecting someone who knows the customer
personally
Which of the following statements illustrates a major difference between project managers and project champions?
Which of the following personnel changes do customers dislike the most?
Project managers spend a considerable amount of time communicating and interacting with project stakeholders. Which of the following is (are) useful reminders for project managers?
I Analyse the work regularly to determine what can be eliminated
II Keep the priorities clear
III If possible, schedule the most interesting activities first
Setting project selection criteria and establishing project priorities is the responsibility of which people on a project?
The role of the executive sponsor is to help the project manager. This help can include which of the following?
I Priority setting
II Assistance in conflict resolution
III Developing the master project plan
IV Setting proper project objectives
Individuals or organisations with active involvement or active interest in a project are called:
Which of the following statements are true when managing a project?
I All decisions must be directed towards achieving the project objectives
II Only the remaining work can be managed
III All decisions must have the sponsor's approval
Who normally has the responsibility for determining "who" will do the work, "where" the work will be done, and "how" the work will be done in a project?
Perception barriers can occur because individuals: