Which of the following statements are true in a cost plus contract?
I The only firm figure is the fee
II The total man-hours cannot be estimated
III The equipment rate is not firm
The make or buy decision is usually made at which stage of the contracting cycle?
When is a FFP contract typically sought by the customer's project manager?
Which of the following is not a function of contract administration?
Which of the following does not affect a contractor's ability to perform the contracted activities after the contract is signed?
Using the data shown below, if the cost of the work is £13,000, then what will be the final price paid by the customer?
Target Cost: £12,000
Target Fee: £1,000
Sharing Ratio: 80% / 20%
Price Ceiling: £14,000
In which of the following types of contract is it most important for the contractor to maintain tight control of cost, schedule and scope changes?
Which of the following should be considered in the negotiation and selection of a contract type?
I The degree of clarity with which the end product is defined
II Price competition
III Period of performance
Using the data shown below, what is the profit at the point of total assumption?
Target Cost: £12,000
Target Fee: £1,000
Sharing Ratio: 80% / 20%
Price Ceiling: £14,000
In which of the following contract types is it easiest to change the scope of the contract?