The impact of a risk event is calculated by multiplying which of the following?
When trying to manage and reduce the risks associated with a project, how should the risk events be grouped?
When changing the scope of a project to lower the associated risk, a project manager should consider the impact on which of the following?
In what type of projects should the principles of risk management be applied?
During which phase of a project is the level of uncertainty the greatest?
A project manager states "I will share this risk with others or totally shift it to them." He/she is exercising which method of risk reduction?
Proper implementation of project management will guarantee which of the following?
What is the ultimate goal of applying the principles of risk management to a project?
Which of the following is correct?
Which of the following is considered a cost of prevention?
I Creating quality control charts
II Rework costs
III Collecting data for use in process improvement efforts
Using the data in the figure below, which supplier would you eliminate if you could eliminate only one vendor (assume that correcting each defect has the same cost per defect in all categories)?
|
|
Supplier |
|
||
|
Defect |
A |
B |
C |
Total |
|
Incorrect Invoice |
IIII |
I |
II |
7 |
|
Incorrect Inventory |
IIII |
II |
I |
8 |
|
Damaged Material |
III |
|
III |
6 |
|
Incorrect Test Doc |
I |
III |
II |
6 |
|
Total |
13 |
6 |
8 |
27 |
Which of the following is (are) true about quality costs when quality management principles are applied?
I Prevention costs may actually rise over time
II Prevention costs and failure costs (internal and external) are inversely related
III Prevention costs and failure costs (internal and external) are directly related