Using the table below, what is the cost performance index (CPI) for WBS Element R?
|
WBS Element |
BCWS |
BCWP |
ACWP |
|
P |
£1,000 |
£1,100 |
£1,150 |
|
Q |
£2,000 |
£1,800 |
£2,100 |
|
R |
£1,000 |
£1,200 |
£1,050 |
|
S |
£2,000 |
£1,900 |
£1,800 |
Using the table below, what is the schedule performance index (SPI) for WBS Element P?
|
WBS Element |
BCWS |
BCWP |
ACWP |
|
P |
£1,000 |
£1,100 |
£1,150 |
|
Q |
£2,000 |
£1,800 |
£2,100 |
|
R |
£1,000 |
£1,200 |
£1,050 |
|
S |
£2,000 |
£1,900 |
£1,800 |
Upon completion of 75% of the project, what should the original schedule and cost estimate that were submitted at the inception of the project be referred to as?
Using the table below, which WBS element has a favourable cost variance of £150?
|
BCWS |
BCWP |
ACWP |
|
|
P |
£1,000 |
£1,100 |
£1,150 |
|
Q |
£2,000 |
£1,800 |
£2,100 |
|
R |
£1,000 |
£1,200 |
£1,050 |
|
S |
£2,000 |
£1,900 |
£1,800 |
What is the difference between the BCWP and the BCWS is referred to as?
Using the table below, which of the following is correct?
|
WBS Element |
BCWS |
BCWP |
ACWP |
|
P |
£1,000 |
£1,100 |
£1,150 |
|
Q |
£2,000 |
£1,800 |
£2,100 |
|
R |
£1,000 |
£1,200 |
£1,050 |
|
S |
£2,000 |
£1,900 |
£1,800 |
Using the table below, which WBS element is behind schedule but under budget?
|
WBS Element |
BCWS |
BCWP |
ACWP |
|
P |
£1,000 |
£1,100 |
£1,150 |
|
Q |
£2,000 |
£1,800 |
£2,100 |
|
R |
£1,000 |
£1,200 |
£1,050 |
|
S |
£2,000 |
£1,900 |
£1,800 |
Budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by which of the following methods?
The formula, EAC = BAC/CPI, assumes which of the following?
Using the table below, which of the following is correct?
|
Month |
BCWS |
BCWP |
ACWP |
|
June |
£34,000 |
£34,000 |
£33,000 |
|
July |
£18,000 |
£16,000 |
£20,000 |
|
August |
£58000 |
£60,000 |
£66,000 |
If the actual cost to date for your project is £12,000 and the budgeted cost for the work scheduled to date is £10,000, then which of the following is correct?
For the figure shown, which of the following is correct?
Using the table below and based upon sterling, what is the actual per cent complete?
Current Period Cumulative
|
Current Period |
Cumulative |
|||||
|
BCWS |
BCWP |
ACWP |
BCWS |
BCWP |
ACWP |
BAC |
|
40 |
45 |
50 |
450 |
500 |
600 |
1,000 |
For the figure shown, what is the status of the project?
In the early stages of a project, the allowable cumulative cost variances are
+/-20%. Given the data below, which elements require an explanation? (Note: figures in millions of pounds).
|
Item |
BCWS |
BCWP |
ACWP |
|
P |
5 |
6 |
8 |
|
Q |
12 |
8 |
9 |
|
R |
13 |
10 |
12 |
|
S |
11 |
11 |
9 |